PRJ-11
DEC 2024 - APR 2025 · A HIGH-MIX ARCHITECTURAL LIGHTING MANUFACTURER IN MONTREAL
Improving Client Drawing Time
Lean Six Sigma · Process Design
Lean Six Sigma Green Belt project: consolidated every document needed to create and verify a shop drawing for 24 beam pattern products into one revision-controlled Excel file in the PDM Vault.
SHOP DRAWING TURNAROUND
7.5 days→5 days
TURNAROUND REDUCTION
—→33%
Problem
Complex-fixture shop drawings took too long. The documents needed to create and verify them were scattered across personal cloud folders, departmental shared folders, archives and a restricted PDM area, with conflicting information between teams.
Approach
- Ran working sessions through the DMAIC phases with the project team, used the lean tools (5 Whys, Fishbone, Detailed Process Maps, Gemba)
- Consolidated everything needed to create and verify a shop drawing for 24 beam pattern products into one Excel file
- Stored in the SolidWorks PDM Vault, under engineering revision control and accessible to every department
Outcome
Shop drawing turnaround for complex beam pattern fixtures 7.5 days to 5 days (a 33% reduction), measured on 45 order lines.
Artifacts
Selected outputs from the project — videos, generated drawings, code, and stakeholder decks.

DETAILED PROCESS MAP — PM (GIVEN TO SD): FROM PO RECEIPT AND ORDER VERIFICATION TO HANDOFF TO SHOP DRAWING.