DEC 2024 - APR 2025 · A HIGH-MIX ARCHITECTURAL LIGHTING MANUFACTURER IN MONTREAL

Improving Client Drawing Time

Lean Six Sigma · Process Design

Lean Six Sigma

Lean Six Sigma Green Belt project: consolidated every document needed to create and verify a shop drawing for 24 beam pattern products into one revision-controlled Excel file in the PDM Vault.

SHOP DRAWING TURNAROUND

7.5 days→5 days

TURNAROUND REDUCTION

—→33%

Problem

Complex-fixture shop drawings took too long. The documents needed to create and verify them were scattered across personal cloud folders, departmental shared folders, archives and a restricted PDM area, with conflicting information between teams.

Approach

  • Ran working sessions through the DMAIC phases with the project team, used the lean tools (5 Whys, Fishbone, Detailed Process Maps, Gemba)
  • Consolidated everything needed to create and verify a shop drawing for 24 beam pattern products into one Excel file
  • Stored in the SolidWorks PDM Vault, under engineering revision control and accessible to every department

Outcome

Shop drawing turnaround for complex beam pattern fixtures 7.5 days to 5 days (a 33% reduction), measured on 45 order lines.

Artifacts

Selected outputs from the project — videos, generated drawings, code, and stakeholder decks.

Detailed process map for the PM flow — order received through email, verified, and handed to shop drawing

DETAILED PROCESS MAP — PM (GIVEN TO SD): FROM PO RECEIPT AND ORDER VERIFICATION TO HANDOFF TO SHOP DRAWING.